Kent County power projects
Kent County, Texas has 7 active power projects totalling 1,630 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,370 MW (84%). The largest single project is Spurland Solar III (322 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
7
1.6 GW capacity
IA signed or later
1
14% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
5
since Sep 2026
Changes in Kent County
New
10/01/2026
Buzzer Butte Solar · Solar · Kent County
Entered the queue at Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911). Projected COD 09/01/2030.
+243 MW
New
10/01/2026
Buzzer Butte 2 Solar · Solar · Kent County
Entered the queue at Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911). Projected COD 09/01/2030.
+243 MW
MW change
10/01/2026
323 → 322 MW
Stage change
09/22/2026
FIS Requested
Stage change
09/15/2026
FIS Requested
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Spurland Solar III | Solar | 322 | Nova Prime Substation | FIS Requested | 12/29/2029 |
| Jay Flat BESS | BESS | 259 | 59908 Novaprime 345kV | FIS Requested | 02/13/2029 |
| Clairemont Solar 1 | Solar | 252 | 59908 Novaprime 345kV | IA Signed | 02/13/2029 |
| Buzzer Butte Solar | Solar | 243 | Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911) | FIS Requested | 09/01/2030 |
| Buzzer Butte 2 Solar | Solar | 243 | Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911) | FIS Requested | 09/01/2030 |
| TEXAS SOLAR NOVA 3 | Solar | 200 | tap 345kV 11305 Dermott - 59904 Cottonwood | FIS Requested | 01/31/2026 |
| Carpet Tech Solar One | Solar | 111 | #59911 MHOS 345 kV | FIS Requested | 06/01/2029 |
| Lake Henry Wind | Wind | 305 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Kent County?
- ERCOT's October 2026 report lists 7 active projects in Kent County totalling 1,630 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.