LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Kent County power projects

Kent County, Texas has 7 active power projects totalling 1,630 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,370 MW (84%). The largest single project is Spurland Solar III (322 MW solar). 1 project has signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
7
1.6 GW capacity
IA signed or later
1
14% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
5
since Sep 2026

Changes in Kent County

New
10/01/2026
Buzzer Butte Solar · Solar · Kent County
Entered the queue at Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911). Projected COD 09/01/2030.
+243 MW
New
10/01/2026
Buzzer Butte 2 Solar · Solar · Kent County
Entered the queue at Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911). Projected COD 09/01/2030.
+243 MW
MW change
10/01/2026
Spurland Solar III · Solar · Kent County
Requested capacity reduced.
323 → 322 MW
Stage change
09/22/2026
Buzzer Butte 2 Solar · Solar · Kent County
Moved from Screening to FIS Requested.
FIS Requested
Stage change
09/15/2026
Buzzer Butte Solar · Solar · Kent County
Moved from Screening to FIS Requested.
FIS Requested

All projects

ProjectFuelMWSubstationStageCOD
Spurland Solar IIISolar322Nova Prime SubstationFIS Requested12/29/2029
Jay Flat BESSBESS25959908 Novaprime 345kVFIS Requested02/13/2029
Clairemont Solar 1Solar25259908 Novaprime 345kVIA Signed02/13/2029
Buzzer Butte SolarSolar243Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911)FIS Requested09/01/2030
Buzzer Butte 2 SolarSolar243Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911)FIS Requested09/01/2030
TEXAS SOLAR NOVA 3Solar200tap 345kV 11305 Dermott - 59904 CottonwoodFIS Requested01/31/2026
Carpet Tech Solar OneSolar111#59911 MHOS 345 kVFIS Requested06/01/2029
Lake Henry WindWind305Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Kent County?
ERCOT's October 2026 report lists 7 active projects in Kent County totalling 1,630 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.