27INR0447 · BESS · Kent County
Jay Flat BESS
Jay Flat BESS is a 259 MW battery storage project in Kent County, Texas, connecting at 59908 Novaprime 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/13/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0447
- Capacity
- 259 MW
- Fuel
- BESS (BA)
- Substation
- 59908 Novaprime 345kV
- County
- Kent County
- Interconnecting entity
- Jay Flat BESS LLC
- Projected COD
- 02/13/2029
- Entered queue
- 01/21/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/21/2025Entered the queue with 259 MW, projected COD 02/13/2029
- 01/21/2025Screening → FIS Requested
Other projects at this substation
| Clairemont Solar 1 | Solar | 252 MW | IA Signed |