LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0294 · Solar · Kent County

Spurland Solar III

Spurland Solar III is a 322 MW solar project in Kent County, Texas, connecting at Nova Prime Substation. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/29/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0294
Capacity
322 MW
Fuel
Solar (PV)
Interconnecting entity
Spurland Solar III, LLC
Projected COD
12/29/2029
Entered queue
08/13/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Capacity 323 → 322 MW
  • 08/13/2026
    Entered the queue with 323 MW, projected COD 12/29/2029
  • 08/13/2026
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.