Hood County power projects

Hood County, Texas has 4 active power projects totalling 761 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 307 MW (40%). The largest single project is Wolf Hollow III (306 MW natural gas). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
4
0.8 GW capacity
IA signed or later
3
75% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
3
since Sep 2026

Changes in Hood County

Stage change
09/18/2026
Apache Hill BESS · BESS · Hood County
Moved from IA Signed to Energization Approved.
Energization Approved
Stage change
09/16/2026
Rain Lily Solar 1 · Solar · Hood County
Moved from FIS Requested to IA Signed.
IA Signed
Stage change
09/16/2026
Rain Lily Storage 1 · BESS · Hood County
Moved from FIS Requested to IA Signed.
IA Signed

All projects

ProjectFuelMWSubstationStageCOD
Wolf Hollow IIIGas3061877 Mitchell Bend 345KVFIS Requested05/31/2027
Apache Hill BESSBESS201363 Hood 138kVEnergization Approved10/31/2026
Rain Lily Solar 1Solar148Tap 138kV #350 ABBYBEND - #363 HOODIA Signed10/15/2028
Rain Lily Storage 1BESS106Tap 138kV #350 ABBYBEND - #363 HOODIA Signed10/15/2028

For residents and landowners

What power projects are planned in Hood County?
ERCOT's October 2026 report lists 4 active projects in Hood County totalling 761 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.