25INR0231 · BESS · Hood County

Apache Hill BESS

Apache Hill BESS is a 201 MW battery storage project in Hood County, Texas, connecting at 363 Hood 138kV. ERCOT's October 2026 report shows it at the Energization Approved stage with a projected commercial operation date of 10/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0231
Capacity
201 MW
Fuel
BESS (BA)
Substation
363 Hood 138kV
Interconnecting entity
APACHE HILL ENERGY CENTER
Projected COD
10/31/2026
Entered queue
10/25/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/18/2026
    IA Signed → Energization Approved
  • 03/10/2026
    FIS Requested → FIS Approved
  • 06/26/2024
    FIS Approved → IA Signed
  • 10/25/2022
    Entered the queue with 201 MW, projected COD 10/31/2026
  • 10/25/2022
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.