25INR0231 · BESS · Hood County
Apache Hill BESS
Apache Hill BESS is a 201 MW battery storage project in Hood County, Texas, connecting at 363 Hood 138kV. ERCOT's October 2026 report shows it at the Energization Approved stage with a projected commercial operation date of 10/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0231
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- 363 Hood 138kV
- County
- Hood County
- Interconnecting entity
- APACHE HILL ENERGY CENTER
- Projected COD
- 10/31/2026
- Entered queue
- 10/25/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/18/2026IA Signed → Energization Approved
- 03/10/2026FIS Requested → FIS Approved
- 06/26/2024FIS Approved → IA Signed
- 10/25/2022Entered the queue with 201 MW, projected COD 10/31/2026
- 10/25/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.