27INR0285 · BESS · Hood County
Rain Lily Storage 1
Rain Lily Storage 1 is a 106 MW battery storage project in Hood County, Texas, connecting at Tap 138kV #350 ABBYBEND - #363 HOOD. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0285
- Capacity
- 106 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138kV #350 ABBYBEND - #363 HOOD
- County
- Hood County
- Interconnecting entity
- Rain Lily Storage One, LLC
- Projected COD
- 10/15/2028
- Entered queue
- 01/10/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/16/2026FIS Requested → IA Signed
- 01/10/2025Entered the queue with 106 MW, projected COD 10/15/2028
- 01/10/2025Screening → FIS Requested
Other projects at this substation
| Rain Lily Solar 1 | Solar | 148 MW | IA Signed |