Frio County power projects
Frio County, Texas has 5 active power projects totalling 924 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 522 MW (57%). The largest single project is Morrow Lake Storage (201 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
0.9 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Frio County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Morrow Lake Storage | BESS | 201 | Morrow Lake Switch 138kV (5896) | FIS Requested | 09/30/2028 |
| Hamlet Solar SLF | Solar | 201 | Tap 138kV #5895 PEARSALL - #5827 MOORE | FIS Requested | 09/04/2029 |
| Hamlet Storage SLF | BESS | 201 | Tap 138kV #5895 PEARSALL - #5827 MOORE | FIS Requested | 09/04/2029 |
| Dilley Solar | Solar | 201 | Tap 138 kV 8212 DILLEY SWITCH AEP - 8613 BIG WELLS | FIS Requested | 06/30/2028 |
| Black Creek BESS | BESS | 120 | New tap between line Bigfoot4A (8221) - MooreSw8 (5827) | FIS Requested | 03/20/2029 |
For residents and landowners
- What power projects are planned in Frio County?
- ERCOT's October 2026 report lists 5 active projects in Frio County totalling 924 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.