21INR0483 · BESS · Frio County
Morrow Lake Storage
Morrow Lake Storage is a 201 MW battery storage project in Frio County, Texas, connecting at Morrow Lake Switch 138kV (5896). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0483
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- Morrow Lake Switch 138kV (5896)
- County
- Frio County
- Interconnecting entity
- Morrow Lake Storage, LLC
- Projected COD
- 09/30/2028
- Entered queue
- 02/07/2020
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/26/2020Screening → FIS Requested
- 02/07/2020Entered the queue with 201 MW, projected COD 09/30/2028
Other projects at this substation
No other projects at this substation.