28INR0461 · Solar · Frio County
Dilley Solar
Dilley Solar is a 201 MW solar project in Frio County, Texas, connecting at Tap 138 kV 8212 DILLEY SWITCH AEP - 8613 BIG WELLS. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0461
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Frio County
- Interconnecting entity
- AETS Development Holdings LLC
- Projected COD
- 06/30/2028
- Entered queue
- 12/19/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/19/2025Entered the queue with 201 MW, projected COD 06/30/2028
- 12/19/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.