28INR0411 · BESS · Frio County
Black Creek BESS
Black Creek BESS is a 120 MW battery storage project in Frio County, Texas, connecting at New tap between line Bigfoot4A (8221) - MooreSw8 (5827). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/20/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0411
- Capacity
- 120 MW
- Fuel
- BESS (BA)
- County
- Frio County
- Interconnecting entity
- Francitas Renewables LLC
- Projected COD
- 03/20/2029
- Entered queue
- 07/29/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/09/2026Screening → FIS Requested
- 07/29/2025Entered the queue with 120 MW, projected COD 03/20/2029