LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Falls County power projects

Falls County, Texas has 13 active power projects totalling 1,509 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,250 MW (83%). The largest single project is RIVERBEND SOLAR SLF (302 MW solar). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
13
1.5 GW capacity
IA signed or later
2
15% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Falls County

COD change
10/01/2026
Roseland Solar · Solar · Falls County
Projected COD moved 11/29/2025 → 10/05/2026. Delay #1 for this project.
+10 mo
COD change
10/01/2026
Roseland Solar II · Solar · Falls County
Projected COD moved 11/29/2025 → 10/05/2026. Delay #1 for this project.
+10 mo
COD change
10/01/2026
Wang Solar SLF · Solar · Falls County
Projected COD moved 03/31/2026 → 01/31/2029. Delay #1 for this project.
+34 mo
COD change
10/01/2026
Wang Storage SLF · BESS · Falls County
Projected COD moved 03/31/2026 → 01/31/2029. Delay #1 for this project.
+34 mo

All projects

For residents and landowners

What power projects are planned in Falls County?
ERCOT's October 2026 report lists 13 active projects in Falls County totalling 1,509 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.