25INR0440 · Solar · Falls County
Bronc Rodeo Solar Project
Bronc Rodeo Solar Project is a 106 MW solar project in Falls County, Texas, connecting at Tap 138 kV Line from Temple Pecan Creek (#3420) to the Cow Bayou Switch (#3385). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/16/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0440
- Capacity
- 106 MW
- Fuel
- Solar (PV)
- County
- Falls County
- Interconnecting entity
- Energiekontor US Texas SP 16 LLC
- Projected COD
- 04/16/2029
- Entered queue
- 05/03/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/12/2023Screening → FIS Requested
- 05/03/2023Entered the queue with 106 MW, projected COD 04/16/2029
Other projects at this substation
No other projects at this substation.