22INR0514 · BESS · Falls County

Wang Storage SLF

COD delayed 1×

Wang Storage SLF is a 0 MW battery storage project in Falls County, Texas, connecting at tap 345kV 3409 LakeCr1 - 3414 TempSS. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/31/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0514
Capacity
0 MW
Fuel
BESS (BA)
Interconnecting entity
BT Yixin Solar, LLC
Projected COD
01/31/2029
Entered queue
09/23/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 03/31/2026 → 01/31/2029 (+34 months)
  • 09/23/2022
    Entered the queue with 0 MW, projected COD 03/31/2026
  • 09/23/2022
    Screening → FIS Requested

Other projects at this substation

Wang Solar SLFSolar145 MWFIS Requested