Dickens County power projects
Dickens County, Texas has 9 active power projects totalling 2,317 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,102 MW (48%). The largest single project is CORUSCANT BESS (418 MW battery storage). 7 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
9
2.3 GW capacity
IA signed or later
7
78% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Dickens County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| CORUSCANT BESS | BESS | 418 | Tap 345kV 59904 COTTONWOOD - 60500 EDITHCLA7A | FIS Requested | 04/18/2027 |
| Spurland Solar I | Solar | 302 | 59908 Nova Prime 345 345kV | IA Signed | 12/30/2028 |
| Outrider BESS | BESS | 302 | Tap 345 kV 59904 Cottonwood (W_CW_345) - 60500 Edith Clarke (EDITHCLA7A) CKT. Approximately distance from the POI to Cottonwood Substation is 11.13 miles and to Edith Clarke Substation 77.6 miles. | IA Signed | 06/26/2029 |
| Sanders Hollow Energy Center | Wind | 293 | Tap 345 kV 59904 Cottonwood (W_CW_345) - 60500 Edith Clarke (EDITHCLA7A) CKT 01 | IA Signed | 06/23/2029 |
| Wolf Spring Storage | BESS | 203 | Tap 345kV 59904 Cotton Wood - 23922 White River Ckt 1 | IA Signed | 08/25/2028 |
| Donegal Solar | Solar | 202 | 59904 Cottonwood 345kV | IA Signed | 11/01/2028 |
| Spurland Solar II | Solar | 202 | 59908 Nova Prime 345 345kV | IA Signed | 12/30/2028 |
| Timberlakes Solar | Solar | 201 | 59904 Cottonwood 345kV | FIS Requested | 11/15/2028 |
| Wolf Spring Solar | Solar | 196 | Tap 345kV 59904 Cotton Wood - 23922 White River Ckt 1 | IA Signed | 08/25/2028 |
| Academy Wind | Wind | 305 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Dickens County?
- ERCOT's October 2026 report lists 9 active projects in Dickens County totalling 2,317 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.