LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0195 · BESS · Dickens County

CORUSCANT BESS

CORUSCANT BESS is a 418 MW battery storage project in Dickens County, Texas, connecting at Tap 345kV 59904 COTTONWOOD - 60500 EDITHCLA7A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/18/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0195
Capacity
418 MW
Fuel
BESS (BA)
Interconnecting entity
AEU Battery Project III LLC
Projected COD
04/18/2027
Entered queue
02/06/2024
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/06/2024
    Entered the queue with 418 MW, projected COD 04/18/2027
  • 02/06/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.