27INR0195 · BESS · Dickens County
CORUSCANT BESS
CORUSCANT BESS is a 418 MW battery storage project in Dickens County, Texas, connecting at Tap 345kV 59904 COTTONWOOD - 60500 EDITHCLA7A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/18/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0195
- Capacity
- 418 MW
- Fuel
- BESS (BA)
- County
- Dickens County
- Interconnecting entity
- AEU Battery Project III LLC
- Projected COD
- 04/18/2027
- Entered queue
- 02/06/2024
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/06/2024Entered the queue with 418 MW, projected COD 04/18/2027
- 02/06/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.