28INR0288 · BESS · Dickens County
Outrider BESS
Outrider BESS is a 302 MW battery storage project in Dickens County, Texas, connecting at Tap 345 kV 59904 Cottonwood (W_CW_345) - 60500 Edith Clarke (EDITHCLA7A) CKT. Approximately distance from the POI to Cottonwood Substation is 11.13 miles and to Edith Clarke Substation 77.6 miles.. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/26/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0288
- Capacity
- 302 MW
- Fuel
- BESS (BA)
- County
- Dickens County
- Interconnecting entity
- Sanders Hollow Energy Center, LLC
- Projected COD
- 06/26/2029
- Entered queue
- 06/05/2025
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/09/2026FIS Requested → IA Signed
- 09/03/2025Screening → FIS Requested
- 06/05/2025Entered the queue with 302 MW, projected COD 06/26/2029
Other projects at this substation
No other projects at this substation.