25INR0173 · BESS · Dickens County
Wolf Spring Storage
Wolf Spring Storage is a 203 MW battery storage project in Dickens County, Texas, connecting at Tap 345kV 59904 Cotton Wood - 23922 White River Ckt 1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 08/25/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0173
- Capacity
- 203 MW
- Fuel
- BESS (BA)
- County
- Dickens County
- Interconnecting entity
- Wolf Spring Solar, LLC
- Projected COD
- 08/25/2028
- Entered queue
- 12/07/2022
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/09/2026FIS Requested → FIS Approved
- 08/14/2024FIS Approved → IA Signed
- 12/07/2022Entered the queue with 203 MW, projected COD 08/25/2028
- 12/07/2022Screening → FIS Requested
Other projects at this substation
| Wolf Spring Solar | Solar | 196 MW | IA Signed |