Delta County power projects
Delta County, Texas has 3 active power projects totalling 187 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 153 MW (82%). The largest single project is Eagle Springs Solar (77 MW solar). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
3
0.2 GW capacity
IA signed or later
3
100% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Delta County
COD change
10/01/2026
Eagle Springs Solar · Solar · Delta County
Projected COD moved 02/23/2027 → 03/29/2027. Delay #1 for this project.
+1 mo
COD change
10/01/2026
Eagle Springs Storage · BESS · Delta County
Projected COD moved 02/23/2027 → 03/29/2027. Delay #1 for this project.
+1 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Eagle Springs Solar | Solar | 77 | Tap Lake Creek Substation (#6835) – Enloe Switching station (#6834) 138 kV Line | IA Signed | 03/29/2027 |
| SERENGETI SOLAR | Solar | 76 | Tap 138kV Enloe Tap (bus# 11806) – Delta sub (bus# 1802) | IA Signed | 09/18/2028 |
| Eagle Springs Storage | BESS | 34 | Tap Lake Creek Substation (#6835) – Enloe Switching station (#6834) 138 kV Line | IA Signed | 03/29/2027 |
For residents and landowners
- What power projects are planned in Delta County?
- ERCOT's October 2026 report lists 3 active projects in Delta County totalling 187 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.