24INR0136 · BESS · Delta County
Eagle Springs Storage
COD delayed 1×
Eagle Springs Storage is a 34 MW battery storage project in Delta County, Texas, connecting at Tap Lake Creek Substation (#6835) – Enloe Switching station (#6834) 138 kV Line. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/29/2027. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0136
- Capacity
- 34 MW
- Fuel
- BESS (BA)
- County
- Delta County
- Interconnecting entity
- Eagle Springs BESS LLC
- Projected COD
- 03/29/2027
- Entered queue
- 10/18/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 02/23/2027 → 03/29/2027 (+1 months)
- 09/17/2025FIS Requested → FIS Approved
- 04/17/2024FIS Approved → IA Signed
- 06/13/2022Screening → FIS Requested
- 10/18/2021Entered the queue with 34 MW, projected COD 02/23/2027
Other projects at this substation
| Eagle Springs Solar | Solar | 77 MW | IA Signed |