25INR0227 · Solar · Delta County
SERENGETI SOLAR
SERENGETI SOLAR is a 76 MW solar project in Delta County, Texas, connecting at Tap 138kV Enloe Tap (bus# 11806) – Delta sub (bus# 1802). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/18/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0227
- Capacity
- 76 MW
- Fuel
- Solar (PV)
- County
- Delta County
- Interconnecting entity
- Abei Energy Green XIV LLC
- Projected COD
- 09/18/2028
- Entered queue
- 11/18/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/03/2026FIS Requested → FIS Approved
- 12/30/2025FIS Approved → IA Signed
- 11/18/2022Entered the queue with 76 MW, projected COD 09/18/2028
- 11/18/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.