Counties / Texas
Dawson County power projects
Dawson County, Texas has 8 active power projects totalling 1,611 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 849 MW (53%). The largest single project is Los Toros Energy Center Solar SLF (402 MW solar). 4 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
8
1.6 GW capacity
IA signed or later
4
50% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Dawson County
MW change
10/01/2026
213 → 214 MW
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Los Toros Energy Center Solar SLF | Solar | 402 | Tap 1167 Mustang_8 to 11206 Dillion_P8 138 kV | FIS Requested | 03/31/2030 |
| Longview Wind | Wind | 353 | Venturi (Bus #59923) | IA Signed | 12/01/2028 |
| Fivemile Wind | Wind | 282 | Tap 138kV Lamesa 138kv (10008) to Jim Payne 138kV (18880) | FIS Requested | 09/23/2029 |
| Red Holly Solar | Solar | 260 | tap 345kV 59900 Longdraw - 79641 Farmland | IA Signed | 09/30/2029 |
| Mesquite Creek Windpower Repower | Wind | 214 | 59900 Long Draw 345 | FIS Requested | 12/31/2027 |
| Red Holly Storage 1 | BESS | 50 | tap 345kV 59900 Longdraw - 79641 Farmland | IA Signed | 05/30/2028 |
| Red Holly Storage | BESS | 50 | tap 345kV 59900 Longdraw - 79641 Farmland | IA Signed | 05/30/2028 |
| Los Toros Energy Center Storage SLF | BESS | 0 | Tap 1167 Mustang_8 to 11206 Dillion_P8 138 kV | FIS Requested | 03/31/2030 |
For residents and landowners
- What power projects are planned in Dawson County?
- ERCOT's October 2026 report lists 8 active projects in Dawson County totalling 1,611 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.