27INR0501 · Wind · Dawson County
Mesquite Creek Windpower Repower
Mesquite Creek Windpower Repower is a 214 MW wind project in Dawson County, Texas, connecting at 59900 Long Draw 345. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0501
- Capacity
- 214 MW
- Fuel
- Wind (WT)
- Substation
- 59900 Long Draw 345
- County
- Dawson County
- Interconnecting entity
- Mesquite Creek Wind LLC
- Projected COD
- 12/31/2027
- Entered queue
- 04/28/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Capacity 213 → 214 MW
- 04/28/2025Entered the queue with 213 MW, projected COD 12/31/2027
- 04/28/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.