27INR0474 · Wind · Dawson County
Fivemile Wind
Fivemile Wind is a 282 MW wind project in Dawson County, Texas, connecting at Tap 138kV Lamesa 138kv (10008) to Jim Payne 138kV (18880). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/23/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0474
- Capacity
- 282 MW
- Fuel
- Wind (WT)
- County
- Dawson County
- Interconnecting entity
- 180 Wind LLC
- Projected COD
- 09/23/2029
- Entered queue
- 04/25/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/25/2025Entered the queue with 282 MW, projected COD 09/23/2029
- 04/25/2025Screening → FIS Requested