Culberson County power projects
Culberson County, Texas has 4 active power projects totalling 1,328 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 740 MW (56%). The largest single project is Buffalo Jump Wind (740 MW wind). 1 project has signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
4
1.3 GW capacity
IA signed or later
1
25% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
3
since Sep 2026
Changes in Culberson County
New
10/01/2026
SunRustler Solar · Solar · Culberson County
Entered the queue at 11082 MAVRKDRW_8 138kV. Projected COD 06/15/2028.
+302 MW
Withdrawn
Unconfirmed
10/01/2026
Hayhurst Texas Solar · Solar · Culberson County
Missing from the latest report, not yet marked withdrawn by ERCOT.
−25 MW
Stage change
09/23/2026
FIS Requested
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Buffalo Jump Wind | Wind | 740 | 1097 Culberson 345 KV | FIS Requested | 07/01/2029 |
| SunRustler Solar | Solar | 302 | 11082 MAVRKDRW_8 138kV | FIS Requested | 06/15/2028 |
| Desert Hill Solar | Solar | 250 | Tap 138kV El Capitan (#10179) - Black River (#1096). | FIS Requested | 07/01/2030 |
| Wallace Solar | Solar | 36 | Delaware River SW (11112) | IA Signed | 05/14/2027 |
| Hayhurst Texas Solar | Solar | 25 | tap 138 kV Three Mile Draw Switch – Horseshoe Springs Switch Line | Withdrawn | 07/17/2026 |
For residents and landowners
- What power projects are planned in Culberson County?
- ERCOT's October 2026 report lists 4 active projects in Culberson County totalling 1,328 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.