LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Culberson County power projects

Culberson County, Texas has 4 active power projects totalling 1,328 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 740 MW (56%). The largest single project is Buffalo Jump Wind (740 MW wind). 1 project has signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
4
1.3 GW capacity
IA signed or later
1
25% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
3
since Sep 2026

Changes in Culberson County

New
10/01/2026
SunRustler Solar · Solar · Culberson County
Entered the queue at 11082 MAVRKDRW_8 138kV. Projected COD 06/15/2028.
+302 MW
Withdrawn
Unconfirmed
10/01/2026
Hayhurst Texas Solar · Solar · Culberson County
Missing from the latest report, not yet marked withdrawn by ERCOT.
−25 MW
Stage change
09/23/2026
SunRustler Solar · Solar · Culberson County
Moved from Screening to FIS Requested.
FIS Requested

All projects

For residents and landowners

What power projects are planned in Culberson County?
ERCOT's October 2026 report lists 4 active projects in Culberson County totalling 1,328 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.