22INR0454 · Solar · Culberson County
Wallace Solar
Wallace Solar is a 36 MW solar project in Culberson County, Texas, connecting at Delaware River SW (11112). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/14/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0454
- Capacity
- 36 MW
- Fuel
- Solar (PV)
- Substation
- Delaware River SW (11112)
- County
- Culberson County
- Interconnecting entity
- Delaware Ranch Solar, LLC
- Projected COD
- 05/14/2027
- Entered queue
- 12/17/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/18/2026FIS Requested → FIS Approved
- 02/07/2022FIS Approved → IA Signed
- 12/17/2020Entered the queue with 36 MW, projected COD 05/14/2027
- 12/17/2020Screening → FIS Requested
Other projects at this substation
No other projects at this substation.