22INR0363 · Solar · Culberson County
Hayhurst Texas Solar
Withdrawn
Hayhurst Texas Solar is a 25 MW solar project in Culberson County, Texas, connecting at tap 138 kV Three Mile Draw Switch – Horseshoe Springs Switch Line. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0363
- Capacity
- 25 MW
- Fuel
- Solar (PV)
- County
- Culberson County
- Interconnecting entity
- Hayhurst Texas Solar, LLC
- Projected COD
- 07/17/2026
- Entered queue
- 08/13/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Listed as withdrawn UNCONFIRMED
- 12/12/2023Energization Approved → Sync Approved
- 11/10/2023IA Signed → Energization Approved
- 04/26/2023FIS Requested → FIS Approved
- 09/09/2021FIS Approved → IA Signed
- 08/13/2020Entered the queue with 25 MW, projected COD 07/17/2026
- 08/13/2020Screening → FIS Requested
Other projects at this substation
No other projects at this substation.