Baylor County power projects
Baylor County, Texas has 6 active power projects totalling 1,891 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,106 MW (58%). The largest single project is Dundee East A Wind (524 MW wind). 2 projects have signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
6
1.9 GW capacity
IA signed or later
2
33% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Baylor County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Dundee East A Wind | Wind | 524 | 345 kV Riley Substation (#6101); AEP | IA Signed | 12/31/2027 |
| Velveteen Solar I | Solar | 502 | Tap into 6076 FOXTAIL- 6100 OKLAUNION | FIS Requested | 10/15/2029 |
| Velveteen Solar II | Solar | 301 | Tap into 6076 FOXTAIL- 6100 OKLAUNION | FIS Requested | 12/15/2029 |
| Dundee East B Wind | Wind | 261 | 345 kV Riley Substation (#6101); AEP | IA Signed | 12/31/2027 |
| Velveteen Solar III | Solar | 201 | Tap into 6076 FOXTAIL- 6100 OKLAUNION | FIS Requested | 12/15/2029 |
| Young Road Solar | Solar | 102 | The POI B is TAP 69 KV LINE AND CREATE NEW BUS BETWEENWESTOVER (784) AND LAKE KEMP SWITCH (782) 69 KV SUB STATIONS. | FIS Requested | 04/30/2028 |
| Diversion Wind | Wind | 300 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Baylor County?
- ERCOT's October 2026 report lists 6 active projects in Baylor County totalling 1,891 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.