Substation / point of interconnection ยท Baylor County
The POI B is TAP 69 KV LINE AND CREATE NEW BUS BETWEENWESTOVER (784) AND LAKE KEMP SWITCH (782) 69 KV SUB STATIONS.
1 active project totalling 102 MW is queued to connect at The POI B is TAP 69 KV LINE AND CREATE NEW BUS BETWEENWESTOVER (784) AND LAKE KEMP SWITCH (782) 69 KV SUB STATIONS. in Baylor County, Texas, according to ERCOT's October 2026 report.
Active capacity
102 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
69 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0514 | Young Road Solar | Solar | 102 | FIS Requested | 04/30/2028 | 0 |