28INR0514 · Solar · Baylor County
Young Road Solar
Young Road Solar is a 102 MW solar project in Baylor County, Texas, connecting at The POI B is TAP 69 KV LINE AND CREATE NEW BUS BETWEENWESTOVER (784) AND LAKE KEMP SWITCH (782) 69 KV SUB STATIONS.. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0514
- Capacity
- 102 MW
- Fuel
- Solar (PV)
- County
- Baylor County
- Interconnecting entity
- reNRG TX 5 LLC
- Projected COD
- 04/30/2028
- Entered queue
- 05/01/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/01/2026Entered the queue with 102 MW, projected COD 04/30/2028
- 05/01/2026Screening → FIS Requested
Other projects at this substation
No other projects at this substation.