29INR0198 · Solar · Baylor County
Velveteen Solar I
Velveteen Solar I is a 502 MW solar project in Baylor County, Texas, connecting at Tap into 6076 FOXTAIL- 6100 OKLAUNION. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/15/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0198
- Capacity
- 502 MW
- Fuel
- Solar (PV)
- Substation
- Tap into 6076 FOXTAIL- 6100 OKLAUNION
- County
- Baylor County
- Interconnecting entity
- Velveteen Solar, LLC
- Projected COD
- 10/15/2029
- Entered queue
- 12/19/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/19/2025Entered the queue with 502 MW, projected COD 10/15/2029
- 12/19/2025Screening → FIS Requested
Other projects at this substation
| Velveteen Solar II | Solar | 301 MW | FIS Requested |
| Velveteen Solar III | Solar | 201 MW | FIS Requested |