ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Victoria County

Tap 138 kV (Bus #5506) FURHMANSB8 - (Bus #5584) VANDERBLTSW8

2 active projects totalling 391 MW are queued to connect at Tap 138 kV (Bus #5506) FURHMANSB8 - (Bus #5584) VANDERBLTSW8 in Victoria County, Texas, according to ERCOT's October 2026 report.

Active capacity
391 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
29INR0244Oak Belt StorageBESS210FIS Requested03/31/20301
29INR0243Oak Belt SolarSolar181FIS Requested03/31/20301