29INR0244 · BESS · Victoria County
Oak Belt Storage
COD delayed 1×
Oak Belt Storage is a 210 MW battery storage project in Victoria County, Texas, connecting at Tap 138 kV (Bus #5506) FURHMANSB8 - (Bus #5584) VANDERBLTSW8. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2030. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0244
- Capacity
- 210 MW
- Fuel
- BESS (BA)
- County
- Victoria County
- Interconnecting entity
- Oak Belt Storage, LLC
- Projected COD
- 03/31/2030
- Entered queue
- 12/17/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/15/2029 → 03/31/2030 (+5 months)
- 12/17/2025Entered the queue with 210 MW, projected COD 10/15/2029
- 12/17/2025Screening → FIS Requested
Other projects at this substation
| Oak Belt Solar | Solar | 181 MW | FIS Requested |