Substation / point of interconnection ยท Pecos County
Tap Bottlebrush (38441) to White Baker (38435) 345kV Line (TNMP)
1 active project totalling 507 MW is queued to connect at Tap Bottlebrush (38441) to White Baker (38435) 345kV Line (TNMP) in Pecos County, Texas, according to ERCOT's October 2026 report.
Active capacity
507 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 30INR0131 | Pecos Flats Wind I | Wind | 507 | FIS Requested | 06/29/2030 | 0 |