ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
30INR0131 · Wind · Pecos County

Pecos Flats Wind I

Pecos Flats Wind I is a 507 MW wind project in Pecos County, Texas, connecting at Tap Bottlebrush (38441) to White Baker (38435) 345kV Line (TNMP). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/29/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
30INR0131
Capacity
507 MW
Fuel
Wind (WT)
Interconnecting entity
Pecos Flats Wind, LLC
Projected COD
06/29/2030
Entered queue
07/07/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/07/2026
    Entered the queue with 507 MW, projected COD 06/29/2030
  • 07/07/2026
    Screening → FIS Requested