Substation / point of interconnection ยท Pecos County

Tap 345kV 60404 Solstice to 38441 Bottlebrush

5 active projects totalling 1,513 MW are queued to connect at Tap 345kV 60404 Solstice to 38441 Bottlebrush in Pecos County, Texas, according to ERCOT's October 2026 report.

Active capacity
1,513 MW
queued at this substation
Active projects
5
5 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
29INR0347Glass Mountain BB Solar 1Solar303FIS Requested03/01/20290
29INR0348Glass Mountain BB Solar 2Solar303FIS Requested03/01/20290
29INR0349Glass Mountain BB Solar 5Solar303FIS Requested10/01/20290
29INR0357Glass Mountain BB Solar 3Solar303FIS Requested10/01/20290
29INR0358Glass Mountain BB Solar 4Solar303FIS Requested10/01/20290