29INR0348 · Solar · Pecos County

Glass Mountain BB Solar 2

Glass Mountain BB Solar 2 is a 303 MW solar project in Pecos County, Texas, connecting at Tap 345kV 60404 Solstice to 38441 Bottlebrush. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0348
Capacity
303 MW
Fuel
Solar (PV)
Interconnecting entity
Glass Mountain Solar II, LLC
Projected COD
03/01/2029
Entered queue
05/29/2026
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/29/2026
    Entered the queue with 303 MW, projected COD 03/01/2029
  • 05/29/2026
    Screening → FIS Requested

Other projects at this substation

Glass Mountain BB Solar 1Solar303 MWFIS Requested
Glass Mountain BB Solar 5Solar303 MWFIS Requested
Glass Mountain BB Solar 3Solar303 MWFIS Requested
Glass Mountain BB Solar 4Solar303 MWFIS Requested