28INR0344 · Solar · Atascosa County

Amphion Solar Phase 3

Amphion Solar Phase 3 is a 115 MW solar project in Atascosa County, Texas, connecting at TAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt-2. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/15/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0344
Capacity
115 MW
Fuel
Solar (PV)
Interconnecting entity
Amphion Solar, LLC
Projected COD
11/15/2029
Entered queue
04/09/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/09/2025
    Entered the queue with 115 MW, projected COD 11/15/2029
  • 04/09/2025
    Screening → FIS Requested

Other projects at this substation

Amphion Solar Phase 2Solar206 MWFIS Requested
Amphion StorageBESS200 MWFIS Requested