LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0343 · Solar · Atascosa County

Amphion Solar Phase 2

Amphion Solar Phase 2 is a 206 MW solar project in Atascosa County, Texas, connecting at TAP 345KV (#5709) Fowlerton - (#5901) SAN MIGUEL LINE Ckt-2. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/15/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0343
Capacity
206 MW
Fuel
Solar (PV)
Interconnecting entity
Amphion Solar, LLC
Projected COD
05/15/2029
Entered queue
04/09/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/09/2025
    Entered the queue with 206 MW, projected COD 05/15/2029
  • 04/09/2025
    Screening → FIS Requested

Other projects at this substation

Amphion Solar Phase 3Solar115 MWFIS Requested
Amphion StorageBESS200 MWFIS Requested