23INR0116 · Solar · Reeves County
Cantaloupe Solar
Cantaloupe Solar is a 307 MW solar project in Reeves County, Texas, connecting at 60716 Saragosa 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0116
- Capacity
- 307 MW
- Fuel
- Solar (PV)
- Substation
- 60716 Saragosa 138kV
- County
- Reeves County
- Interconnecting entity
- Saragosa Del Sol Energy, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 12/01/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/23/2024FIS Requested → IA Signed
- 12/01/2020Entered the queue with 307 MW, projected COD 07/01/2028
- 12/01/2020Screening → FIS Requested
Other projects at this substation
| Bracero Pecan Storage | BESS | 238 MW | IA Signed |