Willacy County power projects
Willacy County, Texas has 4 active power projects totalling 787 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 686 MW (87%). The largest single project is El Sauz Ranch (302 MW wind). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
4
0.8 GW capacity
IA signed or later
2
50% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Willacy County
COD change
10/01/2026
El Sauz Ranch · Wind · Willacy County
Projected COD moved 09/15/2026 → 12/01/2026. Delay #1 for this project.
+3 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| El Sauz Ranch | Wind | 302 | 8663 EL SAUZ POI 345kV | Sync Approved | 12/01/2026 |
| Monte Alto 2 Wind | Wind | 199 | tap 345kV 8318 Rio Hondo - 8383 N Edinburg | IA Signed | 12/31/2028 |
| Los Vientos IB Repower | Wind | 185 | #8319 RIOHONDO 138 kV | FIS Requested | 03/01/2029 |
| Lyford Energy | BESS | 101 | 5745 E Raymondville 138kV | FIS Requested | 09/02/2027 |
For residents and landowners
- What power projects are planned in Willacy County?
- ERCOT's October 2026 report lists 4 active projects in Willacy County totalling 787 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.