20INR0097 · Wind · Willacy County
El Sauz Ranch
COD delayed 1×
El Sauz Ranch is a 302 MW wind project in Willacy County, Texas, connecting at 8663 EL SAUZ POI 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/01/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0097
- Capacity
- 302 MW
- Fuel
- Wind (WT)
- Substation
- 8663 EL SAUZ POI 345kV
- County
- Willacy County
- Interconnecting entity
- El Sauz Ranch Wind, LLC
- Projected COD
- 12/01/2026
- Entered queue
- 06/19/2018
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/15/2026 → 12/01/2026 (+3 months)
- 02/28/2023Energization Approved → Sync Approved
- 09/28/2022IA Signed → Energization Approved
- 10/29/2021FIS Requested → FIS Approved
- 01/27/2021FIS Approved → IA Signed
- 01/31/2019Screening → FIS Requested
- 06/19/2018Entered the queue with 302 MW, projected COD 09/15/2026
Other projects at this substation