LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0097 · Wind · Willacy County

El Sauz Ranch

COD delayed 1×

El Sauz Ranch is a 302 MW wind project in Willacy County, Texas, connecting at 8663 EL SAUZ POI 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/01/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0097
Capacity
302 MW
Fuel
Wind (WT)
Interconnecting entity
El Sauz Ranch Wind, LLC
Projected COD
12/01/2026
Entered queue
06/19/2018
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/15/2026 → 12/01/2026 (+3 months)
  • 02/28/2023
    Energization Approved → Sync Approved
  • 09/28/2022
    IA Signed → Energization Approved
  • 10/29/2021
    FIS Requested → FIS Approved
  • 01/27/2021
    FIS Approved → IA Signed
  • 01/31/2019
    Screening → FIS Requested
  • 06/19/2018
    Entered the queue with 302 MW, projected COD 09/15/2026

Other projects at this substation

No other projects at this substation.