ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Val Verde County power projects

Val Verde County, Texas has 3 active power projects totalling 475 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 372 MW (78%). The largest single project is Lone Bow Solar (278 MW solar). 0 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
3
0.5 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Val Verde County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Lone Bow SolarSolar278Tap 138 kV 8683 Comstock - 60389 CorralFIS Requested06/15/2030
Evans Creek Energy StorageBESS103Comstock 138kV Substation (PSSE Bus #8683)FIS Requested04/01/2028
VISOL 1 SOLARSolar95Tap 138kV 8683 Comstock - 60389 CorralFIS Requested06/30/2028
Pumpville Ranch 1Solar1,000Not listedWithdrawnn/a
Blue Hills WindWind276Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Val Verde County?
ERCOT's October 2026 report lists 3 active projects in Val Verde County totalling 475 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.