Counties / Texas
Val Verde County power projects
Val Verde County, Texas has 3 active power projects totalling 475 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 372 MW (78%). The largest single project is Lone Bow Solar (278 MW solar). 0 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.
Active projects
3
0.5 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Val Verde County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Lone Bow Solar | Solar | 278 | Tap 138 kV 8683 Comstock - 60389 Corral | FIS Requested | 06/15/2030 |
| Evans Creek Energy Storage | BESS | 103 | Comstock 138kV Substation (PSSE Bus #8683) | FIS Requested | 04/01/2028 |
| VISOL 1 SOLAR | Solar | 95 | Tap 138kV 8683 Comstock - 60389 Corral | FIS Requested | 06/30/2028 |
| Pumpville Ranch 1 | Solar | 1,000 | Not listed | Withdrawn | n/a |
| Blue Hills Wind | Wind | 276 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Val Verde County?
- ERCOT's October 2026 report lists 3 active projects in Val Verde County totalling 475 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.