25INR0398 · Solar · Val Verde County

Pumpville Ranch 1

Withdrawn

Pumpville Ranch 1 is a 1,000 MW solar project in Val Verde County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0398
Capacity
1,000 MW
Fuel
Solar
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
04/17/2024
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/17/2024
    Listed as inactive

Other projects at this substation