LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Val Verde County

Tap 138 kV 8683 Comstock - 60389 Corral

1 active project totalling 278 MW is queued to connect at Tap 138 kV 8683 Comstock - 60389 Corral in Val Verde County, Texas, according to ERCOT's October 2026 report.

Active capacity
278 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0419Lone Bow SolarSolar278FIS Requested06/15/20300