LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Mills County power projects

Mills County, Texas has 7 active power projects totalling 1,410 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 776 MW (55%). The largest single project is Priddy Wind (302 MW wind). 3 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
7
1.4 GW capacity
IA signed or later
3
43% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
2
since Sep 2026

Changes in Mills County

MW change
10/01/2026
Starlight Storage · BESS · Mills County
Requested capacity increased.
105 → 209 MW
Withdrawn
09/25/2026
Starlight Storage 2 · BESS · Mills County
Listed as cancelled by ERCOT.
−104 MW

All projects

For residents and landowners

What power projects are planned in Mills County?
ERCOT's October 2026 report lists 7 active projects in Mills County totalling 1,410 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.