ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0438 · BESS · Mills County

Moss Rock Storage

Moss Rock Storage is a 157 MW battery storage project in Mills County, Texas, connecting at #7070 Goldthwaite 138kV. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 12/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0438
Capacity
157 MW
Fuel
BESS (BA)
Interconnecting entity
Invenergy Storage Development LLC
Projected COD
12/31/2029
Entered queue
09/22/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/22/2025
    Entered the queue with 157 MW, projected COD 12/31/2029