La Salle County power projects
La Salle County, Texas has 5 active power projects totalling 1,499 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 716 MW (48%). The largest single project is La Salle Solar (513 MW solar). 2 projects have signed an interconnection agreement or reached a later stage. 4 projects in the county are listed as withdrawn or cancelled.
Active projects
5
1.5 GW capacity
IA signed or later
2
40% of active projects
Withdrawn or cancelled
4
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in La Salle County
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| La Salle Solar | Solar | 513 | Tap 345kV LOBO7A (#80219) - FOWLERTONSW5 (#5709) | IA Signed | 09/13/2028 |
| Crescent C BESS | BESS | 508 | Tap 345kV LOBO7A (#80219) - FOWLERTONSW5 (#5709) CKT#2 | FIS Requested | 02/12/2028 |
| Loma Pinta Solar | Solar | 203 | 5705 Fowlerton 138kV | FIS Requested | 05/31/2028 |
| Loma Pinta Wind | Wind | 197 | 5705 Fowlerton 138kV | IA Signed | 12/31/2026 |
| Hinkell BESS | BESS | 78 | 8612 Reveille 138kV | FIS Requested | 07/01/2027 |
| Vazlon Solar SLF | Solar | 211 | 8619 Encinal - 8627 Lemay Box Bay 138kV line | Withdrawn | 06/30/2028 |
| Dahlia Solar | Solar | 201 | Not listed | Withdrawn | n/a |
| Dahlia BESS | BESS | 103 | Not listed | Withdrawn | n/a |
| Vazlon BESS SLF | BESS | 0 | 8619 Encinal - 8627 Lemay Box Bay 138kV line | Withdrawn | 06/30/2028 |
For residents and landowners
- What power projects are planned in La Salle County?
- ERCOT's October 2026 report lists 5 active projects in La Salle County totalling 1,499 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.