ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

La Salle County power projects

La Salle County, Texas has 5 active power projects totalling 1,499 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 716 MW (48%). The largest single project is La Salle Solar (513 MW solar). 2 projects have signed an interconnection agreement or reached a later stage. 4 projects in the county are listed as withdrawn or cancelled.

Active projects
5
1.5 GW capacity
IA signed or later
2
40% of active projects
Withdrawn or cancelled
4
listed by ERCOT
Changes tracked
2
since Sep 2026

Changes in La Salle County

Withdrawn
09/29/2026
Vazlon Solar SLF · Solar · La Salle County
Listed as inactive by ERCOT.
−211 MW
Withdrawn
09/29/2026
Vazlon BESS SLF · BESS · La Salle County
Listed as inactive by ERCOT.
−0 MW

All projects

ProjectFuelMWSubstationStageCOD
La Salle SolarSolar513Tap 345kV LOBO7A (#80219) - FOWLERTONSW5 (#5709)IA Signed09/13/2028
Crescent C BESSBESS508Tap 345kV LOBO7A (#80219) - FOWLERTONSW5 (#5709) CKT#2FIS Requested02/12/2028
Loma Pinta SolarSolar2035705 Fowlerton 138kVFIS Requested05/31/2028
Loma Pinta WindWind1975705 Fowlerton 138kVIA Signed12/31/2026
Hinkell BESSBESS788612 Reveille 138kVFIS Requested07/01/2027
Vazlon Solar SLFSolar2118619 Encinal - 8627 Lemay Box Bay 138kV lineWithdrawn06/30/2028
Dahlia SolarSolar201Not listedWithdrawnn/a
Dahlia BESSBESS103Not listedWithdrawnn/a
Vazlon BESS SLFBESS08619 Encinal - 8627 Lemay Box Bay 138kV lineWithdrawn06/30/2028

For residents and landowners

What power projects are planned in La Salle County?
ERCOT's October 2026 report lists 5 active projects in La Salle County totalling 1,499 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.