ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท La Salle County

8612 Reveille 138kV

1 active project totalling 78 MW is queued to connect at 8612 Reveille 138kV in La Salle County, Texas, according to ERCOT's October 2026 report.

Active capacity
78 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0395Hinkell BESSBESS78FIS Requested07/01/20270