Counties / Texas
Houston County power projects
Houston County, Texas has 8 active power projects totalling 1,629 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 942 MW (58%). The largest single project is Camino Ranch Storage SLF (298 MW battery storage). 6 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
8
1.6 GW capacity
IA signed or later
6
75% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Houston County
COD change
10/01/2026
Dionysus Solar · Solar · Houston County
Projected COD moved 03/11/2027 → 12/15/2028. Delay #1 for this project.
+21 mo
COD change
10/01/2026
Dionysus Storage · BESS · Houston County
Projected COD moved 03/11/2027 → 12/15/2028. Delay #1 for this project.
+21 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Camino Ranch Storage SLF | BESS | 298 | Tap to Jim English (#3351) – Flat Branch (#3345) 138kV | IA Signed | 12/09/2028 |
| Camino Ranch Solar SLF | Solar | 296 | Tap to Jim English (#3351) – Flat Branch (#3345) 138kV | IA Signed | 12/09/2028 |
| Camino Ranch Storage 2 SLF | BESS | 238 | Tap to Jim English (#3351) – Flat Branch (#3345) 138kV | IA Signed | 12/09/2028 |
| Camino Ranch Solar 2 SLF | Solar | 237 | Tap to Jim English (#3351) – Flat Branch (#3345) 138kV | IA Signed | 12/09/2028 |
| Saint Charles Energy Storage | BESS | 203 | TAP 138kV 3345 FLATBRA_8 - 3351 JIM_ENG_8 | FIS Requested | 04/16/2029 |
| Dionysus Solar | Solar | 153 | Tap 138kV 6733 Mustang Prairie - 6732 Latexo | IA Signed | 12/15/2028 |
| Houston County BESS | BESS | 125 | Tap ETEC 138kV #6733 Mustang Prairie to #6732 Latexo Sub | FIS Requested | 12/31/2029 |
| Dionysus Storage | BESS | 77 | Tap 138kV 6733 Mustang Prairie - 6732 Latexo | IA Signed | 12/15/2028 |
For residents and landowners
- What power projects are planned in Houston County?
- ERCOT's October 2026 report lists 8 active projects in Houston County totalling 1,629 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.