26INR0177 · BESS · Houston County
Dionysus Storage
COD delayed 1×
Dionysus Storage is a 77 MW battery storage project in Houston County, Texas, connecting at Tap 138kV 6733 Mustang Prairie - 6732 Latexo. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/15/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0177
- Capacity
- 77 MW
- Fuel
- BESS (BA)
- County
- Houston County
- Interconnecting entity
- Dionysus Solar, LLC
- Projected COD
- 12/15/2028
- Entered queue
- 06/05/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 03/11/2027 → 12/15/2028 (+21 months)
- 07/31/2026FIS Requested → IA Signed
- 06/05/2023Entered the queue with 77 MW, projected COD 03/11/2027
- 06/05/2023Screening → FIS Requested
Other projects at this substation
| Dionysus Solar | Solar | 153 MW | IA Signed |